A large-scale 2x660 MW super-critical coal-fired thermal power station in Gujarat, India, processes a total condensate recirculation volume of 3,400 m³/h (1,700 m³/h per 660 MW unit). Condensate water collected from steam surface condensers passes through primary condensate polisher filters before entering deep-bed demineralizer beds and high-pressure feedwater heaters.
The plant operates in a hot, humid coastal marine environment using sea water for condenser cooling. Minor condenser tube pin-hole leaks occasionally introduce micro-amounts of sea salts, while load-cycling operations generate continuous particulate magnetite ($Fe_3O_4$) and iron oxide sludge ($10\text{--}30\text{ mg/L}$ TSS).
The power station originally operated classic 2.5-inch string-wound cartridge filter vessels, requiring 360 elements per 660 MW unit (720 elements total across the plant). Cartridge replacement required extensive labor, long unit downtime, and created high consumable supply chain expenses. Plant leadership contracted LEFILTER to modernize their entire condensate filtration infrastructure to optimize operating expenditures (OPEX) and cut maintenance downtime.
Enormous Media Replacement Expense: Consuming over 8,600 standard 40-inch string-wound filter elements per year across both 660 MW units generated annual cartridge procurement and inventory holding costs exceeding USD $180,000.
Prolonged Unit Maintenance Downtime: Replacing 360 string-wound elements per vessel required a 6-man maintenance crew working 6 hours under high ambient heat conditions ($> 42^\circ\text{C}$), extending planned outage windows.
High Disposal and Environmental Footprint: Spent string-wound cartridges contaminated with iron oxide sludge accumulated in large disposal volumes, attracting heavy disposal surcharges under Indian industrial waste management rules.
Uncontrolled Dirt Bypass: Legacy string-wound media loosened under high flow velocities ($> 1,700\text{ m}^3/\text{h}$), causing fiber migration and particulate leakage into the downstream deep-bed ion exchange resins, fouling resin pores.
LEFILTER engineered a complete high-flow condensate filtration upgrade comprising two high-capacity LEFILTER HF-Series Stainless Steel 316L Vessels (one vessel per 660 MW unit), each housing fifteen 60-inch high-flow pleated filter elements.
95.8% Reduction in Element Count: Upgrading to LEFILTER 60-inch high-flow cartridges reduced the total required element count per 660 MW unit from 360 standard string-wound cartridges down to just 15 high-flow elements.
Ergonomic Quick-Davit Vessel Cover: The 316L stainless steel vessels feature a counter-balanced quick-opening davit arm and swing-bolt assembly, allowing a single operator to lift and swing the heavy vessel lid effortlessly.
High Dirt-Holding Pleated Synthetic Media: The multi-layer pleated polypropylene media delivers over 14 m² of surface area per cartridge, capturing up to 6.2 kg of particulate iron oxide scale per 60-inch element before reaching terminal differential pressure.
Zero-Bypass Positive Alignment Core: Each element installs into a machined 316L bottom tube sheet with a twist-lock insertion pin and double O-ring seal, eliminating internal fluid bypass and fiber migration.
Turnkey Overseas Delivery: LEFILTER managed complete vessel fabrication, ASME pressure testing certification, sea logistics to Mundra Port, inland transport to site, and dispatched field engineers for installation tie-in and flow commissioning.

Following 24 months of continuous commercial operation at the Gujarat super-critical power plant, the LEFILTER High-Flow filtration upgrade achieved outstanding financial and operational results:
Massive OPEX Reduction: Annual filter media procurement costs plummeted from USD $180,000 to under USD $34,000 per year, saving the power plant over USD $146,000 annually (75% net consumable cost reduction).
Downtime & Labor Optimization: Element changeout time dropped from 6 hours (6 workers) down to just 25 minutes (2 workers) per vessel, saving over 140 man-hours per maintenance event.
Solid Waste Reduction: Spent filter cartridge disposal mass and volume dropped by 91%, significantly reducing hazardous waste handling surcharges and warehouse storage space.
Resin Bed Protection: Downstream demineralizer resin beds remained 100% free of iron oxide sludge foulants, extending resin backwash intervals from 7 days to over 35 days and reducing resin chemical regeneration costs.
Rapid Capital Amortization: Total capital expenditure for both high-flow vessel skids was fully amortized within 4.1 months of operational startup based solely on cartridge procurement and labor savings.